Update on Wolffork Water Main Project 

Rabun County Water and Sewer Authority (RCWSA) General Manager Brendan Thompson gives an update on the Wolffork Water Main Project. “The contractor, Tom Adams Construction, installed 500 feet of the 8-inch Ductile Iron Pipe (DIP) Water Main this week on Wolffork Baptist Church Road up to Wolffork Road. This includes starting with 60 linear feet in Wolffork Road heading southeast toward US 441. Two miles of pavement milling along Wolffork Road was completed. Traffic Control devices were installed and operational. General clean-up and pipe layout for installation was completed.” The project is anticipated to take another 3-4 months.

Picture by RCWSA.